Photo Gallery
Capital Improvement Project
Church Refurbishment - Fall 2025-Winter 2026
Resurrection Church Pictures Before Refurbishment
Nov. 17-18, 2025 - Nave and Sanctuary Cleared; Kneelers & Pews Removed
Our church beautification process began November 17, 2025. Parish volunteers helped to clear the church as much as possible to allow an open work area as our project got underway. Many hands make light work, as the saying goes. Thanks to all who helped!
Wood Renovators was on-site to remove our pews. Removal started with marking all pew pieces before disassembly. Pew parts were then transported to their Waupaca facility for stripping, repairs and refinishing.
Nov. 19, 2025 - Carpet in Nave and Steps in Sanctuary Removed
Nov. 24, 2025 - Prepping the floor prior to scaffolding
Dec. 1, 2025 - Scaffolding arrived and was unloaded with the help of volunteers
Riehle Decorating arrived on Monday, December 1, to begin the process of repairing the plaster and painting the church interior. Several parish volunteers helped to unload the scaffolding pieces.
Dec. 2-5, 2025 - Riehle Decorating set up the scaffolding
Dec. 9, 2025 - Repairing loose plaster and loose paint
Dec. 11, 2025 - Applying an oil base seal coat to walls and ceiling
Dec. 11, 2025 - Scaffolding in the stairwell of the bell tower
Dec. 15, 2025 - Applying glue and fiberglass to the ceiling
Over 35 5-gallon pails of glue will be applied to the ceiling and walls. Sheets of fiberglass material will be applied over the glue.
Dec. 17, 2025 - Applying glue and fiberglass to the east wall of church and the sanctuary
Dec. 18, 2025 - Glue and fiberglass applied to the east and west walls of church.
Over 80% of the church has the fiberglass layer installed.
Dec. 22, 2025 - Completing the fiberglass layer
Pictured are Jerry Riehle and his grandson, Alex, who drove in from Ohio to visit his grandfather and is working with him while he's here!
Week of Jan. 5, 2026 - Electrical updates to be completed throughout the church
Tennies Electric worked on electrical updates to the church lights and the ceiling light fixtures were taken down for cleaning.
Week of Jan. 12, 2026
Painters working in the main entrance, cry room and stairwell to the choir; Ceiling lights refurbished and awaiting to be set back in place
Week of Jan. 26, 2026
Tennies Electric on site for electrical updates, painting of the main church continues, and Gary Konrath doing his magic with cleaning up the light fixtures during our extreme cold spell.
Wed., Jan. 28, 2026
Dennis and Marg Wiedmeyer made a trip to Wood Renovators in Waupaca to check on the progress of refurbishment of the pews. The pew pieces have been stripped. One of the pew ends shows the new stain color.
Week of Feb. 2, 2026 - Riehle Decorating has completed their work
The painter's truck was loaded with the scaffolding with the help of several volunteers on Thurs., Feb. 5, 2026. With their work completed, the Riehle Decorating crew left for home on Friday, Feb. 6, 2026. Work has now begun on fixing the subfloor and rebuilding the steps in the sanctuary area.
Week of Feb. 9, 2026 - Flooring work continues
This week Randy Heinecke's crew continued to frame the steps for the sanctuary.
The stairs to the choir loft and the choir loft flooring were also sanded in preparation for new stain.
Week of Feb. 16-20, 2026 - Luxury vinyl tile installed in nave & choir loft floor refinished
The work continues with two flooring companies, electrician and carpenters on site.
The choir loft floor was refinished, the sanctuary crucifix was hung and the luxury vinyl tile was installed.
Week of February 23, 2026 - Ceramic tile installed in sanctuary
The ceramic tile was installed in the sanctuary and the altars were delivered. The back altar shows a prototype of the tabernacle cabinet. The shelves to hold the Stations of the Cross were rehung.
Week of March 9, 2026 - Pews reinstalled
Refinished pews were delivered and installed by the Wood Renovators crew. The new main altar was set in place and the newly painted angels positioned in place. John Nettesheim made a surprise visit and checked out the newly installed front pew.
Week of March 16 - The work continues on preparing the sanctuary
The new ambry was hung and the new credence tabel set in place. The photo shows empty ambry cruets in the ambry. The new main altar was raised in order to level the altar stone with the top of the altar.
Week of March 23, 2026 - The replated Tabernacle is installed
Week of March 30, 2026 - Final preparations
The newly painted Last Supper statue is inserted into the main altar. Reupholstered chairs are set in place.
Sunday, April 5 - Resurrection Church reopens for Easter Sunday!
After being closed for 139 days, Resurrection Church reopened on Resurrection Sunday!




































































































































